All Projects
Proposed Project
03Sri Krishna – Sri Rama Campus
Integrated Spiritual, Educational & Rural Development CampusA proposed integrated spiritual, educational, ecological and rural development campus envisioned over approximately 100 acres — a national-level spiritual and educational institution combining spiritual heritage, holistic education, environmental sustainability and rural empowerment.
Master Plan · ₹500 Crore

Campus Area
≈ 100 acres
spiritual, educational & ecological zones
GoShala Capacity
500+
cows initially, expansion to 1,000+
Temple Complex
20 acres
Sri Krishna & Sri Rama temples
Estimated Investment
₹500 Cr
indicative project cost
Region · Karnataka
Major Campus Components
- Sri Krishna Temple
- Sri Rama Temple
- GoShala & Indigenous Breed Protection Center
- Gurukula Concept Residential School
- Vedic Research & Cultural Center
- Organic Farming & Sustainability Zone
- Community Welfare & Rural Development Facilities
Proposed Facilities & Activities
- Meditation and spiritual learning spaces
- Gita classes and spiritual camps
- Ramayana learning and value education
- GoShala with an initial capacity of 500 cows and future expansion to 1,000+
- Veterinary care, fodder cultivation, biogas, Panchagavya and organic manure facilities
- Gurukula education combining school curriculum, Sanskrit, Vedic studies, yoga, meditation, arts, culture, agriculture and skill training
- Vedic research, manuscript preservation and traditional knowledge studies
- Natural farming, herbal cultivation, water harvesting, solar energy and agroforestry
Proposed Land Allocation
- Temple Complex
- 20 acres
- GoShala
- 25 acres
- Gurukula School
- 20 acres
- Organic Farming
- 20 acres
- Residential & Utilities
- 10 acres
- Roads, Landscaping & Water Bodies
- 5 acres
- Total
- 100 acres
Indicative Project Cost
- Land Acquisition
- ₹150 Crore
- Temple Construction
- ₹120 Crore
- GoShala Infrastructure
- ₹40 Crore
- Gurukula School
- ₹100 Crore
- Residential Facilities
- ₹35 Crore
- Solar, Water & Utilities
- ₹20 Crore
- Roads & Landscaping
- ₹15 Crore
- Legal & Administrative Expenses
- ₹5 Crore
- Corpus Fund
- ₹15 Crore
- Total
- ₹500 Crore
All land allocation and cost figures are indicative, as stated in the supplied Detailed Project Report.